2007 cycles
Cycle ending | Predicted work units | Resources | Actual work units | Comments |
|---|---|---|---|---|
75 | 100% | 68 | 3 working week cycle over new years break | |
60 | 100% | 51 | Additional USQ staff support was required | |
50 | 90% | 67 | (1 public holiday) TR starting | |
75 | 100% | 55 | TM starting | |
60 | 100% | 46 | Additional USQ staff support was required | |
60 | 100% | 65 | (end date public holiday) | |
50 | 95% | 60 | cycle start date 2007-03-26 | |
50 | 80% | 25 | Easter long weekend, and 2 new staff members starting) | |
42 | 70% | 40 | 7 day cycle ( 1 public holiday 2 day OOo workshop) | |
80 | 90% | 99 | 1 public holiday | |
100 | 100% | 129 | (includes 40 work units from external development) | |
145 | 60% | 86 | 3 week cycle, DdB on leave 4 days, 1 public holiday, part-time staff member unavailable | |
30 | 60% | 35 | 1 week cycle, 2 part time staff members unavailable | |
60 | 90% | 63 | predicted resources – Digital scholarship tools workshop in the second week (3 days) | |
100 | 100% | 103 | RW absent 1day | |
90 | 90% | 65 | RW absent 1 day; Moving office | |
85 | 85% | 53 | DdB at IDEA road-show 3 days | |
90 | 90% | 72 | DdB on leave 2 days | |
100 | 90% | 75 | SK and LO full-time for 1 week | |
90 | 90% | 126 | DdB on leave 2days, SK and LO full-time for 1 week | |
150 | 70% | 100 | RW (.6) (4 week cycle) – RW absent extra 3 days | |
90 | 90% | 85 | DdB on leave 1 day, LO absent 3 days, (SK unavailable 3days) | |
110 | 120% | 97 | DdB at Clever Collections (4 days), SK LO full-time | |
70 | 120% | 72 | hands-on workshop at USQ 11, 12, 13 of Dec. (SK LO full-time) | |
40 | 120% | 43 | 1 week cycle (SK LO full-time) |