ICE cycle 2008-05-22
Summary
In the previous cycle there were mostly minor updates and bug fixes carried out. We are yet to resolve Subversion issues being experienced with directory conflicts and multi-threading; Also, adding the repository name to URLs has greatly improved usability however, it has also caused other problems, most have now been resolved. Because of these issues we have not yet released another Beta version.
The cycle notes have been published late due to other priorities and there has been no actual cycle meeting due to staff being unavailable. However, we have discussed priorities and they basically remain the same as the last few cycles, resolve the SVN probs and get another Beta release out, as well as setup the SVN repositories for a wider and greater use of ICE at USQ.
Predicted work units: 40 (short staffed)
Overview of completed tasks
Administration
Finalize USQ ICT infrastructure requirements
Application
Subversion issues - Ongoing
Subversion folder conflict handling
Multi-threading issues i.e. Subversion
Investigate options for automatic syncing
Repository name as part of an URL for ICE
Server version testing/development requirements
Continue with stabilization tasks for ICE 2.0 from feedback
Outstanding tasks
How to guides.
Setup of Virtual Machines for ICE Subversion repositories by ICT
ICE Beta 2 release (dependent on SVN issues being resolved)
Configure Windows VM for ICE server
Overview of new tasks
Administration
Setup of Virtual Machines for ICE Subversion repositories by ICT
Presentation to USQ ICT support staff
Create generic USQ skins for new SVN repositories
Configure SVN repositories for ICE:
Courseware repositories (2008, 2009, 2010, general)
Research repository
General repository
ICE Beta 2 release (dependent on SVN issues being resolved)
Application
Subversion issues
Subversion folder conflict handling
Multi-threading issues i.e. Subversion
Investigate options for automatic syncing
Configure Windows VM for ICE server
Continue with stabilization tasks for ICE 2.0 from feedback
About the cycle notes
The cycle notes are used to summarize the outcomes of the completed cycle and provide stake-holders with an overview of the tasks for the next cycle. They are also used to raise any issues for discussion and provide other information for those who are unable to attend the meetings. Specific information on tasks to be completed are available in the ticketing system, see below.
More information
http://ice.usq.edu.au/trac/milestone/icecycle%202008-05-22
http://ice.usq.edu.au/trac/roadmap